Clarke Energy has secured a series of major orders with Tamar Energy, a developer of anaerobic digestion projects in the UK, to supply combined heat and power systems for their biogas plants.

  • Clarke Energy secures orders of biogas engines for four sites across the UK including Holbeach, Farleigh, Retford and Halstead
  • Tamar Energy has placed initial orders for six gas engines with a total renewable power output of 8MWe, enough to power over 20,000 UK homes

Tamar Energy is a renewable energy business that focuses solely on anaerobic digestion. Tamar Energy has the long-term aim of building a UK network of 40 plants and producing 100 MW of renewable base-load electricity.

The UK Department for Energy and Climate Change (DECC) and Department for Energy Food and Rural Affairs (Defra) recently presented their Anaerobic Digestion Strategy and Action Plan. This plan outlines a road map for increasing energy from waste through anaerobic digestion as part of their commitment to be the ‘greenest Government ever’ with a target of supporting up to three to five Terawatt hours of electricity from anaerobic digestion by 2020.

Tamar Energy has placed initial orders with Clarke Energy for four of GE Power & Water’s J420 and two J416 containerised Jenbacher gas engines. GE Jenbacher gas engines are renowned for their electrical efficiency and robust performance on challenging gases such as biogas. The gas engines are fitted with heat exchangers to facilitate cogeneration, recovering heat as hot water for use in the heating of the digesters and pasteurisation.

The gas engines’ performance will be supported by Clarke Energy’s service network which is the largest network of dedicated gas engine service engineers in the UK.

The biogas engines will be deployed at four of Tamar Energy’s anaerobic digestion plants in the UK. These include:

  • Holbeach in Lincolnshire – 1 x J420, total electrical output 1.5 MW
  • Retford in Yorkshire – 2 x J420, total electrical output 3.0 MW
  • Farleigh in Wiltshire – 1 x J420, total electrical output 1.5 MW
  • Halstead in Essex – 2 x J416, total electrical output 2.2 MW

Anaerobic digestion plants that use gas engines are able to generate base-load renewable electricity. This contrasts to wind turbines and photovoltaic panels which typically generate only when the wind blows or the sun-shines. They are also a form of embedded generation, which helps to generate power close to the site of use and hence avoid losses associated with electrical transmission. In addition, their ability to produce digestate a soil improver that is pasteurised by the heat from CHP engines can be used to offset energy intensive chemical fertilisers.

Dan Poulson, Engineering and Strategy Director of Tamar Energy outlines their decision:

Our plans are to develop a network of anaerobic digestion plants across the UK in order to help meet the country’s renewable energy targets. Clarke Energy’s technical solution, backed up by the largest network of dedicated gas engine specialists in the UK, were key factors in us awarding these orders.

Jamie Clarke, Chief Executive Officer of Clarke Energy states:

We are delighted to have secured this framework contract with Tamar Energy. Tamar Energy’s plans to develop a network of biogas projects across the UK will make a significant contribution to the country’s renewable energy targets. We are pleased to help support Tamar Energy with the Jenbacher product and our network of gas engine service engineers’.

Back To Top